CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7

Published: December 29, 2023

December 28, 2023, Thursday

BT 7 Team Members: R Distura, R Sombilla, J Doce, J Arroyo, R Daliva and R. Parohinog
Accomplished:
1. Installed temporary 25 KVA rental transformer for the Municipality of Sigma (LGU-Sigma)
2. Change duplex #6 to 1.0 insulated at President Roxas Substation, Cabugcabug, President Roxas
3. Installed cut-out at DITO cellsite at Barangay Binuntucan, Pontevedra
4. Replacement of damaged 25 KVA rental transformer at Barangay Timpas, Panitan