January 2-5, 2024, Tuesday to Friday

BT 9 Team Members: H. Delfin, RV Faderugao, J Flores, A Daliva, S Dela Torre and F Distura
Accomplished:
1. Pull out of idle materials and transfer of metering from Barangay Bilao to Barangay Lonoy, Sapian
2. Clearing of lines from Timpas, Panitan to portion of the municipality of Sigma
3. Replacement of rotten pole at Sitio Kawa-kawa, Barangay Agdalipe, Pontevedra
4. Installation of temporary 50 KVA transformer for the Municipality of Jamindan Municipal Fiesta
5. Pull out temporary 25 KVA transformer at Barangay Sta. Cruz, Dumalag