WEEKLY AND JOINT TEAM ACCOMPLISHMENTS BT 8 AND LINEMEN TRAINEES

Published: January 13, 2024

January 8-12, 2024, Monday to Friday

BT 8 Team Members: G Condino, C Daliva, NM Distura, M Umiten IF Valiente and A Ordas
Accomplished:
1. Continued grounding installation on single phase line laterals
a. Bato, Roxas city
b. Oakwood subdivision, Mongpong, Roxas City
c. Banica Elementary School
d. Laterals single phase line along Tanza, Roxas City area
2. Line clearing
a. Bato, Roxas City
b. Oakwood subdivision, Mongpong, Roxas City
c. Banica Elementary School
d. Tanza Roxas city
3. Replacement of damaged 100 KVA transformer at Gomez Ricemill, Dinginan, Roxas City

Other News

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

December 6, 2024 (Friday) Affected Areas: ๐๐‘๐†๐˜. ๐Œ๐ˆ๐‹๐ˆ๐๐ˆ๐‹๐ˆ, ๐“๐€๐๐™๐€, ๐“๐ˆ๐™๐€, ๐๐€๐“๐Ž, & ๐๐Ž๐‘๐“๐ˆ๐Ž๐ ๐Ž๐…...

read more

Follow Us

Other Related Posts