(0963) 043 8339 info@capelco.com

WEEKLY ACCOMPLISHMENTS BT7

Published: January 14, 2024

January 8- 12, 2024, Monday to Friday

BT& Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
Accomplished:
1. Replacement of rotten Pole and transfer of metering at Barangay Dulangan, Pilar
2. Pull out and transfer of 50 KVA and additional 37.5KVA transformer at Barangay Poblacion Ilaya, Pontevedra
3. Pull out of idle materials at Barangay Lantangan, Pontevedra
4. Installation of 2 units of recloser at President Roxas Substation
5. Continued construction of 3-phase Line at bypass road Poblacion, Tapaz

Other News

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ“, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Sunday) Affected Areas: ๐Œ๐”๐๐ˆ๐‚๐ˆ๐๐€๐‹๐ˆ๐“๐˜ ๐Ž๐… ๐‰๐€๐Œ๐ˆ๐๐ƒ๐€๐ & ๐๐Ž๐‘๐“๐ˆ๐Ž๐ ๐Ž๐…...

read more

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’ , ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Saturday) Affected Areas: ๐๐”๐‘๐†๐Ž๐’ ๐ˆ๐‹๐€๐–๐Ž๐ƒ / ๐๐‹๐€๐™๐€ / ๐‘๐ˆ๐™๐€๐‹ / ๐“๐€๐๐๐”๐„ /...

read more

Follow Us

Other Related Posts