January 15-16, 2024, Monday and Tuesday

BT2 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
Accomplished:
1. Replacement of 3 pieces of rotten pole (mano-mano) at Sitio Malingin, Barangay Guintas, Jamindan
2. Relocation of pole and line clearing at Sitio Dodo, Barangay Agtambi, Dao
3. Replacement of rotten pole at Sitio Proper, Barangay Agtambi, Dao

Other News

๐‚๐€๐๐„๐‹๐‚๐Ž ๐‡๐Ž๐‹๐ƒ๐’ ๐‚๐‡๐‘๐ˆ๐’๐“๐Œ๐€๐’ ๐€๐๐ƒ ๐“๐‡๐€๐๐Š๐’๐†๐ˆ๐•๐ˆ๐๐† ๐‚๐„๐‹๐„๐๐‘๐€๐“๐ˆ๐Ž๐

The Capiz Electric Cooperative, Inc. (CAPELCO) successfully held its Christmas and Thanksgiving...

read more

๐‚๐€๐๐„๐‹๐‚๐Ž ๐‚๐Ž๐๐ƒ๐”๐‚๐“๐’ ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐‘๐„๐†๐”๐‹๐€๐‘ ๐Œ๐„๐„๐“๐ˆ๐๐† ๐€๐๐ƒ ๐“๐‡๐€๐๐Š๐’๐†๐ˆ๐•๐ˆ๐๐† ๐Œ๐€๐’๐’

The CAPELCO family once again came together in faith and fellowship for the First Friday Holy...

read more

Follow Us

Other Related Posts