CONSOLIDATED TEAM ACCOMPLISHMENTS BT7

Published: January 24, 2024

January 22, 2024, Monday

BT7 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
Accomplished:
1. Relocation of pole at Barangay Malag-it, Pontevedra
2. Installation of temporary 2 units of 50 KVA transformer at Maayon plaza for Maayon Municipal Fiesta
3. Hole digging and installation of 40 ft pole at Barangay Malag-it, Pontevedra

Other News

๐‚๐€๐๐„๐‹๐‚๐Ž ๐‡๐Ž๐‹๐ƒ๐’ ๐‚๐‡๐‘๐ˆ๐’๐“๐Œ๐€๐’ ๐€๐๐ƒ ๐“๐‡๐€๐๐Š๐’๐†๐ˆ๐•๐ˆ๐๐† ๐‚๐„๐‹๐„๐๐‘๐€๐“๐ˆ๐Ž๐

The Capiz Electric Cooperative, Inc. (CAPELCO) successfully held its Christmas and Thanksgiving...

read more

๐‚๐€๐๐„๐‹๐‚๐Ž ๐‚๐Ž๐๐ƒ๐”๐‚๐“๐’ ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐‘๐„๐†๐”๐‹๐€๐‘ ๐Œ๐„๐„๐“๐ˆ๐๐† ๐€๐๐ƒ ๐“๐‡๐€๐๐Š๐’๐†๐ˆ๐•๐ˆ๐๐† ๐Œ๐€๐’๐’

The CAPELCO family once again came together in faith and fellowship for the First Friday Holy...

read more

Follow Us

Other Related Posts