CONSOLIDATED TEAM ACCOMPLISHMENTS BT7

Published: January 24, 2024

January 22, 2024, Monday

BT7 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
Accomplished:
1. Relocation of pole at Barangay Malag-it, Pontevedra
2. Installation of temporary 2 units of 50 KVA transformer at Maayon plaza for Maayon Municipal Fiesta
3. Hole digging and installation of 40 ft pole at Barangay Malag-it, Pontevedra