NGCP POWER INTERRUPTION PIGGY-BACKING ACTIVITIES

Published: February 4, 2024

February 4, 2024, Sunday

Panitan Construction and Maintenance Operation
As scheduled: From 6:00 AM to 6:00 PM
In Actual: From 6:16 AM to 5:08 PM (Feeder 2) and 5:12 PM (Feeder 4)
Maximizing the time that power is out due to NGCPs preventive maintenance activities, construction and maintenance crews conducted their own parallel activities and accomplished the following:
1. Relocation of pole at Barangay Bailan, Pontevedra
2. Replacement of rotten pole at Barangay Timpas, Panitan (C4 structure)
3. Replacement of rotten pole at Barangay Timpas, Panitan (C3 structure)
4. Replacement of rotten cross arm at Barangay Malapad Cogon, Sigma (.C2 structure converted to C8)
5. Replacement of rotten pole at Barangay Malapad Cogon, Sigma (C4 Structure)
6. Relocation of 3-phase line at Barangay Parian, Sigma
7. Line clearing from Poblacion Sigma to Mianay blade disconnect switch
Working Crews:
BT1 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
BT2 Team Members: K Cordovero, A Ferrer and R Distura
BT7 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
ML-1 Team Members: M. Bitoon, J. Pinuela and E. Bithao