WEEKLY AND CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

February 4 to February 8, 2024, Sunday to Thursday

BT 8 Team Members: G Condino, C Daliva, NM Distura, M Umiten JF Valiente and A Ordas
Accomplished:
1. Assisted power interruption/correction of line at feeder 1-R, Roxas Avenue to Barangay Punta Tabuc, Roxas City
 Replacement of C9-C14 structure beside east west bank
 Retensioning of 3-phase line 1-span serving BPI bank
 Realignment of cross arm C-14 and installation of stirrup connectors besides Puregold
 Retensioning of 2-span 3-phase line at Pavia St. Cor. Premier de Mayo St.
 Clearing of mango tree near Chinese school, Punta Tabuc, Roxas City
2. Continued grounding installation and line clearing at Pueblo de Panay Lawaan, Roxas City
3. Repair of disconnected primary line and correction of 3-phase cut out jumper at Lawaan, Roxas City
4. Replacement of damaged cross arm at Sitio Caduolan, Banica, Roxas City
5. Installation of temporary connection for Chinese New Year lantern as requested by the Provincial Government at Roxas Avenue, Roxas City w/ m7-crew
 1-50 KVA and 1- 37.5 KVA
6.Retirement of 5 units of 35 feet old poles affected by road widening from Sta. Cruz, Ivisan to Bolo, Roxas City
7. Installation of additional 2- span underbuilt line at Dayao, Roxas City
8. Relocation of pole at Luna Novicio St. Barangay I, Roxas City, 4 units of J6 structure and rehabilitation of 7 kilowatt hour meters

Other News

EMERGENCY POWER INTERRUPTION

𝐄𝐌𝐄𝐑𝐆𝐄𝐍𝐂𝐘 𝐏𝐎𝐖𝐄𝐑 𝐈𝐍𝐓𝐄𝐑𝐑𝐔𝐏𝐓𝐈𝐎𝐍 Date: 𝐒𝐄𝐏𝐓𝐄𝐌𝐁𝐄𝐑 𝟐𝟒, 𝟐𝟎𝟐𝟔 (Thursday) Affected Areas: 𝐅𝐄𝐄𝐃𝐄𝐑 𝐅𝟑 - Whole...

read more

EMERGENCY POWER INTERRUPTION

𝐄𝐌𝐄𝐑𝐆𝐄𝐍𝐂𝐘 𝐏𝐎𝐖𝐄𝐑 𝐈𝐍𝐓𝐄𝐑𝐑𝐔𝐏𝐓𝐈𝐎𝐍 Date: 𝐒𝐄𝐏𝐓𝐄𝐌𝐁𝐄𝐑 𝟐𝟒, 𝟐𝟎𝟐𝟔 (Thursday) Affected Areas: 𝐅𝐄𝐄𝐃𝐄𝐑 𝐅𝟑 - Whole...

read more

EMERGENCY POWER INTERRUPTION

𝐒𝐂𝐇𝐄𝐃𝐔𝐋𝐄𝐃 𝐏𝐎𝐖𝐄𝐑 𝐈𝐍𝐓𝐄𝐑𝐑𝐔𝐏𝐓𝐈𝐎𝐍 SEPTEMBER 26, 2026 (Sabado nga adlaw) Ang CAPELCO magapatigayon sang...

read more

Follow Us

Other Related Posts