WEEKLY AND CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

February 26 to March 1, 2024, Monday to Friday

BT 8 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas
Accomplished:
1. Continued grounding installation Feeder 8-R Pueblo de Panay line section, Lawaan to Dinginan, Roxas City
2. Rehabilitation of lines due to fire incident at Barangay VII, Roxas City
• Isolation of damaged lines
• Repair and replacement of wires (4 span O/S lines)
• Re-energization of member-consumer-owners (MCOs) not directly affected by incident
3. Installation of 37.5 KVA transformer for the exclusive use of Mary Ann Bellion apartment, Tanque, Roxas City
4. Installation of 25 KVA transformer for the exclusive use of Seaoil Philippine Corporation, Banica, Roxas City
5. Rehabilitation of lines at Barangay Basiao, Ivisan
• Replacement of rotten pole
• Rehabilitation of 15 kilowatt hour meters
• Installation of additional 25 KVA transformer

Other News

EMERGENCY POWER INTERRUPTION

𝐄𝐌𝐄𝐑𝐆𝐄𝐍𝐂𝐘 𝐏𝐎𝐖𝐄𝐑 𝐈𝐍𝐓𝐄𝐑𝐑𝐔𝐏𝐓𝐈𝐎𝐍 Date: 𝐒𝐄𝐏𝐓𝐄𝐌𝐁𝐄𝐑 𝟐𝟒, 𝟐𝟎𝟐𝟔 (Thursday) Affected Areas: 𝐅𝐄𝐄𝐃𝐄𝐑 𝐅𝟑 - Whole...

read more

EMERGENCY POWER INTERRUPTION

𝐄𝐌𝐄𝐑𝐆𝐄𝐍𝐂𝐘 𝐏𝐎𝐖𝐄𝐑 𝐈𝐍𝐓𝐄𝐑𝐑𝐔𝐏𝐓𝐈𝐎𝐍 Date: 𝐒𝐄𝐏𝐓𝐄𝐌𝐁𝐄𝐑 𝟐𝟒, 𝟐𝟎𝟐𝟔 (Thursday) Affected Areas: 𝐅𝐄𝐄𝐃𝐄𝐑 𝐅𝟑 - Whole...

read more

EMERGENCY POWER INTERRUPTION

𝐒𝐂𝐇𝐄𝐃𝐔𝐋𝐄𝐃 𝐏𝐎𝐖𝐄𝐑 𝐈𝐍𝐓𝐄𝐑𝐑𝐔𝐏𝐓𝐈𝐎𝐍 SEPTEMBER 26, 2026 (Sabado nga adlaw) Ang CAPELCO magapatigayon sang...

read more

Follow Us

Other Related Posts