CONSOLIDATED TEAM ACCOMPLISHMENTS BT1

Published: March 4, 2024

February 27-28, 2024 and March 2, 2024, Tuesday to Wednesday and Saturday

BT1 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
Accomplished:
1. Pull out of idle 15 KVA transformer at San Vicente, Tapaz
2. Pull out of idle materials and transfer kilowatt hour meters at Sitio Ulilik, Barangay Sta. Ana, Tapaz
3. Replacement of damaged transformer at Poblacion Ilaya, Cuartero
4. Installation of 50 KVA rental transformer at Barangay Agcabugao, Cuartero
5. Installation of 25 KVA rental transformer at Camp Candidad, Timpas, Panitan
6. Replacement of rotten pole and transfer of kilowatt hour meters at Sitio Bugtong Bukid, Sta. Fe, Pilar

Other News

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ“, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Sunday) Affected Areas: ๐Œ๐”๐๐ˆ๐‚๐ˆ๐๐€๐‹๐ˆ๐“๐˜ ๐Ž๐… ๐‰๐€๐Œ๐ˆ๐๐ƒ๐€๐ & ๐๐Ž๐‘๐“๐ˆ๐Ž๐ ๐Ž๐…...

read more

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’ , ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Saturday) Affected Areas: ๐๐”๐‘๐†๐Ž๐’ ๐ˆ๐‹๐€๐–๐Ž๐ƒ / ๐๐‹๐€๐™๐€ / ๐‘๐ˆ๐™๐€๐‹ / ๐“๐€๐๐๐”๐„ /...

read more

Follow Us

Other Related Posts