WEEKLY AND CONSOLIDATED TEAM ACCOMPLISHMENTS BT 10

Published: March 18, 2024

March 11-15, 2024, Monday to Friday

BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas
Accomplished:
1. Rehabilitation of line/extension of 2 span secondary line and transfer of kilowatt hour meters at Barangay Inzo Arnaldo Village, Roxas City (Barangay Visitation Priority)
2. Retirement of 6 units of old poles and materials affected by DPWH road widening project at Barangay Lonoy, Roxas City
3. Continued grounding installation for Feeder B2,
โ€ข From Roxas City Airport including clearing and cutting tree branches
โ€ข From Sitio San Juan, Baybay and Barangay Culasi, Roxas City
4.Replacement of broken spool insulator at crossing San Antonio, Baybay, Roxas City

Other News

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Saturday) Affected Areas: ๐…๐„๐„๐ƒ๐„๐‘ ๐Ÿ - ๐ต๐‘…๐บ๐‘Œ. ๐ด๐ท๐ฟ๐ด๐‘Š๐ด๐‘, ๐ฟ๐‘‚๐ถ๐‘‡๐‘ˆ๐บ๐ด๐‘, ๐ฟ๐ผ-๐‘‚๐‘๐บ,...

read more

Follow Us

Other Related Posts