CONSOLIDATED TEAM ACCOMPLISHMENTS BT7

Published: March 20, 2024

March 16 โ€“ 17 and March 19 - 20, 2024, Friday to Saturday and Tuesday and Wednesday

BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
Accomplished:
1. Installation of 50 KVA rental transformer at Sitio RBM, Barangay Agsirab, Dumarao
2. Insertion of pole and clearing of lines at Barangay Ilas Sur, Dao
3. Replacement of 2 units of rotten pole (mano-mano) and transfer kilowatt hour meter at BAPA 3, Barangay Bergante, Mambusao
4. Relocation of pole and transfer kilowatt hour meters at Barangay Pagbunitan, Sigma
5. Rehabilitation of line from duplex #6 to duplex # 2 and transfer kilowatt hour meters, additional service pole and insertion of wood pole due to low elevation secondary line at Barangay Ilas Sur, Dao
6. Installation of 25 KVA rental transformer at Barangay Duyoc, Dao
7. Installation of 50 KVArental transformer at Barangay Sta. Cruz, Dumalag
8. Installation of 50 KVA rental transformer at Barangay Ongol, Ilawod, Dumarao