POST SCHEDULED POWER INTERRUPTION REPORT

Published: April 23, 2024

April 23, 2024, Tuesday

From 6:00 AM to 3:00 PM
Areas affected:
• Barangay Cabugcabug, Badiangon, Bayuyan, Sto. Niño, Carmencita, Goce and Manoling, President Roxas.
Barangay Yating, San Silvestre and Tabun-acan, Pilar.
Accomplished: Conversion of line from V-phase to 3-phase and line clearing operation
Working Crews:
BT7 Team Members: A Dangan, R Daliva, J Penuela and PP Fuentes
BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
ML-1 Team Members: M Bitoon, R Duriasm JJ Bereber and E Bithao
#NLBEnterprises – Line clearing contractor