POST EMERGENCY POWER INTERRUPTION REPORT

Published: April 25, 2024

April 25, 2024, Thursday

ย Barangay Monteflor, Pilar
Power out: 1:00 AM
Power restored: 9:30 AM
Cause: Disconnected 3-span of single-phase line hit by toppled Mahogany tree
Responding Crew: #TeamPRAOMaintenance and BAPA Crew
Team Leader: B Dellota
Team Members: J Paderes, N Tumlos, J Dorado and A Canas