April 24 and April 27-28, 2024, Wednesday and Saturday to Sunday

BT 11 Team Members: J Saron, R Fabella, M Batuampo and M Deocampo
Accomplished:
1. Correction of low elevation wire, duplex and telecom wires from Barangay Cagay to Barangay Dayao
2. Installation of intermediate pole
3. Extension of line and rehabilitation of kilowatt hour meters at Sitio Ilaya, Dinginan, Roxas City (FB Complaint)