RESPONSE TO 48TH AGMA PRIORITIES

Published: May 8, 2024

May 6, 2024, Monday

Accomplished: Rephasing of lines from secondary line to single phase and installation of additional 25 KVA transformer due to low voltage at Barangay Quios, Panitan
Working crew:
BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog

Other News

CAPELCO Emergency Response Plan

CAPELCO has activated its ๐„๐ฆ๐ž๐ซ๐ ๐ž๐ง๐œ๐ฒ ๐‘๐ž๐ฌ๐ฉ๐จ๐ง๐ฌ๐ž ๐๐ฅ๐š๐ง (ERP) in anticipation of the potential impact of...