PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION

Published: May 12, 2024

May 12, 2024, Sunday

Taking time that power is out due to the Preventive Maintenance Servicing of Dao Substation, CAPELCO’s construction crew and the maintenance crew of Dao Area Office conducted parallel activities to make use of the time that power is out.
Accomplished:
1. Replacement of 2 units of rotten poles at Barangay Nasunogan, Dao
2. Replacement of rotten pole and rotten cross arm at Barangay Angub, Cuartero
3. Installation of 1 unit of pole at Dao Substation
4. Replacement of polymer insulator/ suspension from Sta. Cruz, Dumalag to Suhot Blade Disconnect Switch at Barangay Dolores, Dumalag
5. Line clearing operation
Working Crew:
BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes
BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas
ML 2 Team Members: A Dangan, E Dublado, R Delfin, J Escalada, N Estorque and L Acejo
#NLBEnterprises – Line clearing contractor