PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION

Published: May 12, 2024

May 12, 2024, Sunday

Taking time that power is out due to the Preventive Maintenance Servicing of Dao Substation, CAPELCOโ€™s construction crew and the maintenance crew of Dao Area Office conducted parallel activities to make use of the time that power is out.
Accomplished:
1. Replacement of 2 units of rotten poles at Barangay Nasunogan, Dao
2. Replacement of rotten pole and rotten cross arm at Barangay Angub, Cuartero
3. Installation of 1 unit of pole at Dao Substation
4. Replacement of polymer insulator/ suspension from Sta. Cruz, Dumalag to Suhot Blade Disconnect Switch at Barangay Dolores, Dumalag
5. Line clearing operation
Working Crew:
BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes
BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas
ML 2 Team Members: A Dangan, E Dublado, R Delfin, J Escalada, N Estorque and L Acejo
#NLBEnterprises โ€“ Line clearing contractor

Other News

Ang Presyo sang Kuryente sa Bulan sang Hunyo Nag Nubo!

๐Œ๐€๐€๐˜๐Ž ๐๐†๐€ ๐๐€๐‹๐ˆ๐“๐€! ๐€๐๐† ๐๐‘๐„๐’๐˜๐Ž ๐’๐€๐๐† ๐Š๐”๐‘๐˜๐„๐๐“๐„ ๐’๐€ ๐๐”๐‹๐€๐ ๐’๐€๐๐† ๐‡๐”๐๐˜๐Ž ๐๐€๐† ๐๐”๐๐Ž! Humalin Abril 2025,...

read more

Stay Connected with CAPELCO

๐’๐“๐€๐˜ ๐‚๐Ž๐๐๐„๐‚๐“๐„๐ƒ ๐–๐ˆ๐“๐‡ ๐‚๐€๐๐„๐‹๐‚๐Ž in this holiday season and pay your Electric Bills on or before due...

read more

Follow Us

Other Related Posts