May 11, 2024, Saturday

Areas affected: Municipality of Sapian, Mambusao and Jamindan
As scheduled: From 5:30 AM to 1:30PM
In Actual
From 5:32 AM to 12:57 AM for Feeder M2 and M3 (Municipality of Mambusao and Jamindan)
From 5:32 AM to 1:50 PM for Feeder M1 (Municipality of Sapian)
Accomplished: Annual Preventive Maintenance Servicing of Mambusao Substation and Maninang Tapping Point