CONSOLIDATED TEAM ACCOMPLISHMENTS BT 9

Published: May 17, 2024

May 14-15, 2024, Tuesday to Wednesday

BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
Accomplished:
1. Installation of temporary 37.5 KVA transformer at Sitio Bakante, Barangay Consolacion, Dumalag
2. Installation of temporary 75 KVA transformer at Barangay Salong, Tapaz
3. Installation of temporary 25 KVA transformer at Barangay Bo. Fe, Jamindan
4. Clearing of lines at Barangay San Esteban, Pilar with ML1
ML 1 Team Members: M Bitoon, R Durias, JJ Bereber and E Bithao