PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION

Published: May 19, 2024

May 18, 2024, Saturday

Taking time that power is out due to the Preventive Maintenance Servicing of President Roxas Substation, CAPELCO’s construction crew and the maintenance crew of President Roxas Area Office conducted parallel activities to make use of the time that power is out.
Accomplished
• Replacement of polymer insulator/suspension at Feeder L1/L3 from President Roxas Substation to Poblacion, Pilar
• Relocation of pole at Barangay Hipona, Pontevedra
• Replacement of pole at Barangay Manayupit, Maayon
• Replacement of damaged suspension of 69 kV line at arangay Vizcaya, President Roxas
• Line clearing operation
• Hotspot correction by President Roxas Maintenance Team
Working Crews:
BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo
ML 1 Team Members: M Bitoon, R Durias, JJ Bereber and E Bithao
ML 2 Team Members: A Dangan, E Dublado, R Delfin, J Escalada, N Estorque and L Acejo
#NLBEnterprises – Line clearing contractor