POST SCHEDULED POWER INTERRUPTION REPORT

Published: May 19, 2024

May 18, 2024, Saturday

As scheduled: From 5:30 AM to 1:30 PM
In actual: From 5:30 AM to 12:26 PM
Areas affected: All Feeders connected to President Roxas Substation
Feeder L1- Municipality of Pilar
Feeder L2 โ€“ Municipality of President Roxas
Feeder L3 – Island Barangays of Pontevedra and Upland Barangays of Maayon.
Accomplished: Completed Preventive Maintenance Servicing of President Roxas Substation.