CONSOLIDATED TEAM ACCOMPLISHMENTS BT6

May 24-25, 2024, Friday and Saturday

BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes
Accomplished:
1. Relocation of pole at Barangay Cagay, Roxas City (DITO paid project)
2. Pull out of 37.5 KVA transformer at Arcabalo Milibili and installation of 37.5 KVA Transformer at Dinginan, Roxas City (religious fiesta)
3. Installation of 25 KVA transformer at Cabugao, Roxas City (Religious Fiesta)
4. Installation of intermediate pole at Ilamnay, Panay (FB complaint)

Other News

EMERGENCY POWER INTERRUPTION

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐ Date: ๐’๐„๐๐“๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ” (Thursday) Affected Areas: ๐…๐„๐„๐ƒ๐„๐‘ ๐…๐Ÿ‘ - Whole...

read more

EMERGENCY POWER INTERRUPTION

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐ Date: ๐’๐„๐๐“๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ” (Thursday) Affected Areas: ๐…๐„๐„๐ƒ๐„๐‘ ๐…๐Ÿ‘ - Whole...

read more

EMERGENCY POWER INTERRUPTION

๐’๐‚๐‡๐„๐ƒ๐”๐‹๐„๐ƒ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐ SEPTEMBER 26, 2026 (Sabado nga adlaw) Ang CAPELCO magapatigayon sang...

read more

Follow Us

Other Related Posts