PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION

Published: June 2, 2024

June 1, 2024, Saturday

Making use that power is out at Dao Substation, the construction crew conducted their own activities accomplishing the following:
โ€ข Relocation of 3-Phase line at Sitio Utod, San Miguel, Dumalag (FB Complain)
โ€ข Insertion of pole at Barangay San Miguel, Dumalag (C1 structure)
Working Crews:
BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
ML 1 Team Members: M Bitoon, R Durias, JJ Bereber and E Bithao
#NLBEnterprises โ€“ Line Clearing contractor

Other News

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Saturday) Affected Areas: ๐…๐„๐„๐ƒ๐„๐‘ ๐Ÿ - ๐ต๐‘…๐บ๐‘Œ. ๐ด๐ท๐ฟ๐ด๐‘Š๐ด๐‘, ๐ฟ๐‘‚๐ถ๐‘‡๐‘ˆ๐บ๐ด๐‘, ๐ฟ๐ผ-๐‘‚๐‘๐บ,...

read more

Follow Us

Other Related Posts