PREPARATORY ACTIVITY FOR THE ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION

Published: June 2, 2024

June 1, 2024, Saturday

Accomplished:
1. Installation of 1 span 3phase line @ Dao substation to energize Dao from Feeder 4 Panitan Substation via looping connection
2. Connection of jumper from 13.2 to 69 kV at bypass road Barangay Amaga, Sigma to energize Dao from Feeder 4 Panitan Substation via looping connection