PREPARATORY ACTIVITY FOR THE ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION

June 1, 2024, Saturday

Accomplished:
1. Installation of 1 span 3phase line @ Dao substation to energize Dao from Feeder 4 Panitan Substation via looping connection
2. Connection of jumper from 13.2 to 69 kV at bypass road Barangay Amaga, Sigma to energize Dao from Feeder 4 Panitan Substation via looping connection

Other News

EMERGENCY POWER INTERRUPTION

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐ Date: ๐’๐„๐๐“๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ” (Thursday) Affected Areas: ๐…๐„๐„๐ƒ๐„๐‘ ๐…๐Ÿ‘ - Whole...

read more

EMERGENCY POWER INTERRUPTION

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐ Date: ๐’๐„๐๐“๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ” (Thursday) Affected Areas: ๐…๐„๐„๐ƒ๐„๐‘ ๐…๐Ÿ‘ - Whole...

read more

EMERGENCY POWER INTERRUPTION

๐’๐‚๐‡๐„๐ƒ๐”๐‹๐„๐ƒ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐ SEPTEMBER 26, 2026 (Sabado nga adlaw) Ang CAPELCO magapatigayon sang...

read more

Follow Us

Other Related Posts