CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7

Published: June 20, 2024

June 10-11, 16, 2024, Monday to Tuesday and Sunday

BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
Accomplished:
1. Pull out of temporary transformers at Cuartero, as follows:
• Barangay Agdahon – 25 KVA
• Barangay Agnaga – 25 KVA
• Barangay Balingasag – 50 KVA
• Barangay Poblacion Ilaya – 50 KVA
• Dao Area Office – 2 units of 25 KVA
2. Pull out of 25 KVA temporary transformer at East and West Villaflores, Maayon
3. Relocation of pole at Poblacion Ilaya, Panitan
4. Relocation of pole and rehabilitation of kilowatt hour meters meter with line clearing at Sitio Agdodoyan, Barangay Timpas, Panitan

Other News

Ang Presyo sang Kuryente sa Bulan sang Hunyo Nag Nubo!

𝐌𝐀𝐀𝐘𝐎 𝐍𝐆𝐀 𝐁𝐀𝐋𝐈𝐓𝐀! 𝐀𝐍𝐆 𝐏𝐑𝐄𝐒𝐘𝐎 𝐒𝐀𝐍𝐆 𝐊𝐔𝐑𝐘𝐄𝐍𝐓𝐄 𝐒𝐀 𝐁𝐔𝐋𝐀𝐍 𝐒𝐀𝐍𝐆 𝐇𝐔𝐍𝐘𝐎 𝐍𝐀𝐆 𝐍𝐔𝐁𝐎! Humalin Abril 2025,...

read more

Stay Connected with CAPELCO

𝐒𝐓𝐀𝐘 𝐂𝐎𝐍𝐍𝐄𝐂𝐓𝐄𝐃 𝐖𝐈𝐓𝐇 𝐂𝐀𝐏𝐄𝐋𝐂𝐎 in this holiday season and pay your Electric Bills on or before due...

read more

Follow Us

Other Related Posts