Accomplished:
1. Pull out of temporary transformers at Cuartero, as follows:
• Barangay Agdahon – 25 KVA
• Barangay Agnaga – 25 KVA
• Barangay Balingasag – 50 KVA
• Barangay Poblacion Ilaya – 50 KVA
• Dao Area Office – 2 units of 25 KVA
2. Pull out of 25 KVA temporary transformer at East and West Villaflores, Maayon
3. Relocation of pole at Poblacion Ilaya, Panitan
4. Relocation of pole and rehabilitation of kilowatt hour meters meter with line clearing at Sitio Agdodoyan, Barangay Timpas, Panitan