POST SCHEDULED POWER INTERRUPTION REPORT

Published: June 21, 2024

June 19, 2024, Wednesday

From 8:00 AM to 4:30 PM
Areas affected: Barangays Concepcion, San Roque, San Agustin, San Martin and portion of Sta. Teresa, Dumalag
Accomplished: Relocation, conversion and clearing of lines
Working Crews:
BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura