POST SCHEDULED POWER INTERRUPTION REPORT

Published: June 27, 2024

June 27, 2024, Thursday

Areas affected: Feeder B2 – City Mall to Baybay and Culasi including portion of San Juan Baybay
As scheduled: From 5:00 AM to 6:00 AM
In actual:
5:00 AM open and closed B2 Feeder
5:00 AM open Disconnect Switch at Rombohan Baybay Roxas city
5:53 AM closed Disconnect Switch at Rombohan Baybay Roxas city
Accomplished: Replacement of damaged cross arm at Baybay, Roxas City
Working Crew: #TeamRCAOMaintenance
Team Members: T Daliva and S Calipong

Other News

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ“, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Sunday) Affected Areas: ๐Œ๐”๐๐ˆ๐‚๐ˆ๐๐€๐‹๐ˆ๐“๐˜ ๐Ž๐… ๐‰๐€๐Œ๐ˆ๐๐ƒ๐€๐ & ๐๐Ž๐‘๐“๐ˆ๐Ž๐ ๐Ž๐…...

read more

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’ , ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Saturday) Affected Areas: ๐๐”๐‘๐†๐Ž๐’ ๐ˆ๐‹๐€๐–๐Ž๐ƒ / ๐๐‹๐€๐™๐€ / ๐‘๐ˆ๐™๐€๐‹ / ๐“๐€๐๐๐”๐„ /...

read more

Follow Us

Other Related Posts