POST SCHEDULED EMERGENCY POWER INTERRUPTION REPORT

Published: June 29, 2024

JUNE 28, 2024, Friday

As scheduled: From 12:00 NN to 12:45 PM
In actual: From 12:00 NN to 12:24 PM
Areas affected:
• Feeder 2 – Municipality of Pontevedra (except those those connected at President Roxas Substation), portion of Panay and portion of Panitan
• Feeder 4 – portion of Panitan, portion of Sigma and the Municipality of Ivisan
Accomplished: Hotspot Correction of loose bolt at the Blade Disconnect Switch at Panitan Sub Station.