(0963) 043 8339 info@capelco.com

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7

Published: July 14, 2024

July 7-10, 2024, Sunday to Wednesday

BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes with K Cordovero and R Distura, Jr.
Accomplished:
1. Replacement of 2 units of rotten pole (mano-mano) and resagging of single phase line at Barangay Agbanog, Pontevedra
2. Replacement of 3 units of rotten poles at Sitio Bugaan, Barangay Dulangan, Pilar
3. Replacement of damaged 25 KVA transformer at Sitio Maurisan, Barangay Enseรฑagan, Panitan
4. Relocation of line at Barangay Gabuan, Roxas City (Done during the scheduled power interruption)
5. Pull out of temporary 25 KVA transformer 25 at Barangay Dapdapan, Sapian
6. Replacement of rotten and toppled pole at Sitio Tabon, Poblacion, Sapian
7. Replacement of 3 units of rotten poles (mano-mano) at Barangay Roosevelt, Tapaz

Other News

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ“, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Sunday) Affected Areas: ๐Œ๐”๐๐ˆ๐‚๐ˆ๐๐€๐‹๐ˆ๐“๐˜ ๐Ž๐… ๐‰๐€๐Œ๐ˆ๐๐ƒ๐€๐ & ๐๐Ž๐‘๐“๐ˆ๐Ž๐ ๐Ž๐…...

read more

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’ , ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Saturday) Affected Areas: ๐๐”๐‘๐†๐Ž๐’ ๐ˆ๐‹๐€๐–๐Ž๐ƒ / ๐๐‹๐€๐™๐€ / ๐‘๐ˆ๐™๐€๐‹ / ๐“๐€๐๐๐”๐„ /...

read more

Follow Us

Other Related Posts