CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7

Published: July 22, 2024

July 15-16 and July 19-21, 2024, Monday to Tuesday and Friday to Sunday

BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes with K Cordovero and R Distura, Jr.
Accomplished:
1. Line clearing of single-phase line at Sitio Bailan, Barangay Pinay, Mambusao
2. Installation 37.5 KVA at Barangay Sta. Ana, Tapaz to address low voltage concerns
3. Line clearing at Sitio ilaya, Barangay Duran, Dumalag
4. Replacement of rotten pole at Barangay Lus-onan, Panay (Done during the scheduled power interruption)
5. Installation of intermediate pole and install down guy and resagging of secondary line at Barangay Indayagan, Maayon
6. Hauling of damaged 25 KVA transformer at Sitio Tagbakan, Barangay Concepcion, Dumalag
7. Installation of 2 units of intermediate pole, replacement of rotten pole and line clearing operation at Barangay San Miguel, Tapaz