CONSOLIDATED TEAM ACCOMPLISHMENT BT9

Published: July 30, 2024

July 23-27, 2024, Tuesday to Saturday

BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
Accomplished:
1. Relocation and insertion of intermediate pole (mano2x) at Sitio Pangpang Barangay Balucuan, Sigma (FB Complain)
2. Relocation of 3-phase line and transfer of metering including pull out of idle materials at Barangay San Esteban, Pilar
3. Replacement of rotten pole and rehabilitation of metering at Sitio Tabong, Barangay Atiplo, Mambusao
4. Replacement of rotten pole and rehabilitation of metering for 2 poles at Barangay Poblacion Norte, Sigma
5. Replacement of rotten pole (mano-mano) at Barangay Timpas, Panitan
6. Digging and hauling at Barangay Anhawon, panay
7. Installation of additional 25 KVA transformer and 37.5 KVA transformer at Barangay Solo, Pontevedra to address low voltage problem
8. Hotspot correction at Panitan substation
9. Clearing of lines at from Barangay Bailan to Poblacion, Pontevedra
10. Replacement of jumper at Barangay Tacas, Pontevedra