CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

Published: July 30, 2024

July 22-26, 2024, Monday

ย to FridayBT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
Accomplished:
1. Replacement of 3 units of disconnect switch to cutout at Barangay Bungsuan, Dumarao
2. Replacement of rotten pole at Riverside Barangay Poblacion Ilawod, Dumarao
3. Conversion of line #2 to 1/0 insulated at Poblacion Ilaya, Dumarao
4. Replacement of 30 feet steel pole to 35 feet and correction of low elevation primary lines at Sitio Sinandigan, Barangay Mianay, Sigma
5. Relocation of new 3-phase line at Barangay San Esteban, Pilar
6. Installation of intermediate 35 feet pole and transfer of metering at Barangay San Esteban, Pilar
7. Installation of service pole 30 feet pole at Barangay San Esteban, Pilar
8. Installation of additional 25 KVA transformer and replacement of #6 duplex runner to #2 at Barangay Poblacion Ilawod, Dumarao
9. Relocation of guy wire at Barangay Guinotos, Dumarao
10. Energization new 3-phase line and 3 units of 250 KVA transformer at Dumalag Public Market with (Edgar dumagpi team)
11. Installation of 50 KVA temporary transformer at Poblacion Ilaya, Dumarao