POST SCHEDULED POWER INTERRUPTION REPORT

Published: August 5, 2024

August 3, 2024, Saturday

As scheduled: From 7:00 AM to 4:00 PM
In actual:
Poblacion Dumalag – From 7:00 AM to 8:01 AM
Tapaz – From 7:00 AM to 3:39 PM
Areas affected: Barangay Dolores, Duran, Sta. Teresa, Dumalag and the entire Municipality of Tapaz
Accomplished: Line upgrading and line clearing
Working Crews:
BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes
BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
BT 10 Team Members: G Condino, C Daliva, NM Distura, R Daliva and A Ordas
ML 1 Team Members: M Bitoon, R Durias, JJ Bereber and E Bithao
ML 3 Team Members โ€“ K Cordovero and R Distura Jr
#NLBEnterprises โ€“ Line clearing contractor

Other News

๐—–๐—”๐—ฃ๐—˜๐—Ÿ๐—–๐—ข ๐—ฆ๐—จ๐—ฃ๐—ฃ๐—ข๐—ฅ๐—ง๐—ฆ ๐—•๐—ข๐—ฌ๐—ฆ ๐—”๐—ก๐—— ๐—š๐—œ๐—ฅ๐—Ÿ๐—ฆ ๐—ช๐—˜๐—˜๐—ž ๐Ÿฎ๐Ÿฌ๐Ÿฎ๐Ÿฑ

๐‚๐€๐๐„๐‹๐‚๐Ž is honored to support the ๐‘ฉ๐’๐’š๐’” ๐’‚๐’๐’… ๐‘ฎ๐’Š๐’“๐’๐’” ๐‘พ๐’†๐’†๐’Œ ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ“: "๐™Ž๐™š๐™–๐™ง๐™˜๐™ ๐™›๐™ค๐™ง ๐™ฉ๐™๐™š ๐˜ฝ๐™ค๐™ฎ๐™จ & ๐™‚๐™ž๐™ง๐™ก๐™จ ๐˜พ๐™–๐™ฅ๐™ž๐™ฏ...

read more

Follow Us

Other Related Posts