POST SCHEDULED POWER INTERRUPTION REPORT

Published: August 5, 2024

August 3, 2024, Saturday

As scheduled: From 7:00 AM to 4:00 PM
In actual:
Poblacion Dumalag – From 7:00 AM to 8:01 AM
Tapaz – From 7:00 AM to 3:39 PM
Areas affected: Barangay Dolores, Duran, Sta. Teresa, Dumalag and the entire Municipality of Tapaz
Accomplished: Line upgrading and line clearing
Working Crews:
BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes
BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
BT 10 Team Members: G Condino, C Daliva, NM Distura, R Daliva and A Ordas
ML 1 Team Members: M Bitoon, R Durias, JJ Bereber and E Bithao
ML 3 Team Members โ€“ K Cordovero and R Distura Jr
#NLBEnterprises โ€“ Line clearing contractor

Other News

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ“, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Sunday) Affected Areas: ๐Œ๐”๐๐ˆ๐‚๐ˆ๐๐€๐‹๐ˆ๐“๐˜ ๐Ž๐… ๐‰๐€๐Œ๐ˆ๐๐ƒ๐€๐ & ๐๐Ž๐‘๐“๐ˆ๐Ž๐ ๐Ž๐…...

read more

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

Date: ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’ , ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ’ (Saturday) Affected Areas: ๐๐”๐‘๐†๐Ž๐’ ๐ˆ๐‹๐€๐–๐Ž๐ƒ / ๐๐‹๐€๐™๐€ / ๐‘๐ˆ๐™๐€๐‹ / ๐“๐€๐๐๐”๐„ /...

read more

Follow Us

Other Related Posts