POST SCHEDULED POWER INTERRUPTION REPORT

Published: August 15, 2024

August 14, 2024, Wednesday

As Scheduled: From 4:00 AM to 6:00 AM
In actual:
Feeder 2R โ€“ From 4:05 AM to 5:10 AM
Feeder 4R โ€“ From 4:05 AM to 5:04 AM
Reason: transfer of line connection of Barangay Tanza, Health Centrum at Barangay Banica and Barangay Bato to Feeder 2R.
Working Crews:
BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas
BT 11 Team Members: J Saron, R Fabella, M Batuampo, J Degones and M Deocampo