POST EMERGENCY POWER INTERRUPTION REPORT

Published: September 25, 2024

September 24, 2024, Tuesday

From 7:15 PM to 10:00 PM

Reason: Disconnected jumper due to broken insulator due to intrusion of gecko into the distribution line
Actions taken: Replacement of broken insulator, replacement of power fuse and reconnection of jumpers
Areas affected: Feeders L1, L2 and L3 covering the areas of the Municipality of Pilar, President Roxas, portion of Pontevedra and upland Maayon.