POST SCHEDULED POWER INTERRUPTION REPORT

Published: October 7, 2024

October 4, 2024, Friday

As scheduled: From 6:00 AM to 3:00 PM
In actual: From 6:00 AM to 12:31 PM
Accomplished: Relocation of DPWH road widening affected Project and line clearing operation
Areas affected:
• Roxas City – Barangays Adlawan, Liong, Loctugan, portion of Barangay Bago and portion of Barangay Jumaguicjic.
• Panay – Barangay Bago Grande.
• Panitan – Portion of Barangay Salocon
Areas that experienced momentary interruption:
• Barangay Poblacion Ilawod, Poblacion Ilaya, portion of Timpas and portion of Intampilan and Salocon
• Whole municipality of Panay and Barangay Olotayan, Roxas City
• Seven eleven (7-11) Lawaan, Homesite Lawaan, Katipunan Homesite, portion of Malipayon Village, Bangkiling Tiza, whole of Milibili, Datiles St., Tiza, Graceville Subd., Capiz Gym, Lomboy St., Catmon St., Tambis St., St. Joseph Subd., Tiza, The Health Centrum Hospital, Sitio Caduolan, Banica, portion of Brgy. Banica, Bato, Roxas City, Tanza, Roxas City, DepEd Roxas, Kapis Mansion, CRAAHS, East Groove, Banica and Mongpong Dulunan.
Working Crews:
BT 8 Team Members: R Distura, R Sombilla, JP Hachuela, J Arroyo and R Parohinog
BT 9 Team Members: H Delfin, RV Fadirugao, D Celoso Jr, A Daliva and F Distura
BT 10 Team Members: G Condino, C Daliva, NM Distura, JF Vallente and A Ordas
ML 1 Team Members – M Bitoon, R Durias, JJ Bereber and E Bithao
ML 2 Team Members: L Acejo, E Dublado, R Delfin, J Escalada and N Estorque
ML 3 Team Members – K Cordovero, R Distura Jr. and J Jaguio
#NLBEnterprises – Line clearing contractor