POST SCHEDULED POWER INTERRUPTION REPORT

October 12, 2024, Saturday

As scheduled: From 6:00 AM to 3:00 PM
In actual: From 6:00 AM to 2:55 PM
Areas affected: Feeder D2 โ€“ Municipality of Dumalag and Tapaz
Accomplished: Energization of new 3-phase line affected by DPWH Road Widening Project and line clearing operation
Working Crews:
BT 6 Team Members: R Dili, R Delfin, N Sibugan, M Umiten and R Fuentes
BT 7 Team Members: A Dangan, R Daliva, J Doce, MA Bolinas and PP Fuentes
BT 8 Team Members: R Distura, R Sombilla, JP Hachuela, J Arroyo and R Parohinog
BT 9 Team Members: H Delfin, RV Fadirugao, D Celoso Jr, A Daliva and F Distura
BT 10 Team Members: G Condino, C Daliva, NM Distura, JF Vallente and A Ordas
ML 1 Team Members โ€“ M Bitoon, R Durias, JJ Bereber and E Bithao
ML 3 Team Members โ€“ K Cordovero, R Distura Jr. and J Jaguio
#NLBEnterprises – Line clearing contractor

Other News

EMERGENCY POWER INTERRUPTION

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐ Date: ๐’๐„๐๐“๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ” (Thursday) Affected Areas: ๐…๐„๐„๐ƒ๐„๐‘ ๐…๐Ÿ‘ - Whole...

read more

EMERGENCY POWER INTERRUPTION

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐ Date: ๐’๐„๐๐“๐„๐Œ๐๐„๐‘ ๐Ÿ๐Ÿ’, ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ” (Thursday) Affected Areas: ๐…๐„๐„๐ƒ๐„๐‘ ๐…๐Ÿ‘ - Whole...

read more

EMERGENCY POWER INTERRUPTION

๐’๐‚๐‡๐„๐ƒ๐”๐‹๐„๐ƒ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐ SEPTEMBER 26, 2026 (Sabado nga adlaw) Ang CAPELCO magapatigayon sang...

read more

Follow Us

Other Related Posts