POST SCHEDULED POWER INTERRUPTION REPORT

Published: October 25, 2024

October 24, 2024, Thursday

As scheduled: From 8:30 AM to 5:00 PM
In actual: From 8:30 AM to 4:30 PM
Areas affected: 7-11 Jamindan, Jamindan Water System, Barangays Agambulong, San Vicente, Pangabat and Masgrau, Jamindan.
Accomplished: Line clearing operation, replacement of rotten poles and relocation of poles
Working crews:
BT 8 Team Members: R Distura, R Sombilla, JP Hachuela, J Arroyo and R Parohinog
BT 9 Team Members: H Delfin, RV Fadirugao, D Celoso Jr, A Daliva and F Distura
ML 1 Team Members โ€“ M Bitoon, R Durias, JJ Bereber and E Bithao
ML 2 Team Members: L Acejo, E Dublado, R Delfin, J Escalada and N Estorque
#NLBEnterprises – Line clearing contractor

Other News

๐—–๐—”๐—ฃ๐—˜๐—Ÿ๐—–๐—ข ๐—ฆ๐—จ๐—ฃ๐—ฃ๐—ข๐—ฅ๐—ง๐—ฆ ๐—•๐—ข๐—ฌ๐—ฆ ๐—”๐—ก๐—— ๐—š๐—œ๐—ฅ๐—Ÿ๐—ฆ ๐—ช๐—˜๐—˜๐—ž ๐Ÿฎ๐Ÿฌ๐Ÿฎ๐Ÿฑ

๐‚๐€๐๐„๐‹๐‚๐Ž is honored to support the ๐‘ฉ๐’๐’š๐’” ๐’‚๐’๐’… ๐‘ฎ๐’Š๐’“๐’๐’” ๐‘พ๐’†๐’†๐’Œ ๐Ÿ๐ŸŽ๐Ÿ๐Ÿ“: "๐™Ž๐™š๐™–๐™ง๐™˜๐™ ๐™›๐™ค๐™ง ๐™ฉ๐™๐™š ๐˜ฝ๐™ค๐™ฎ๐™จ & ๐™‚๐™ž๐™ง๐™ก๐™จ ๐˜พ๐™–๐™ฅ๐™ž๐™ฏ...

read more

Follow Us

Other Related Posts