POST SCHEDULED POWER INTERRUPTION REPORT

Published: November 5, 2024

October 31, 2024, Thursday

As scheduled: From 6:00 AM to 3:00 PM
In Actual: From 6:00 AM to 12:30 PM
Areas Affected:
Roxas City – portion of Brgy. Adlawan, Loctugan and Bago.
Panay – Brgy. Bago Grande, Candual, Agbanban and portion of Calitan.
Accomplished: Relocation of lines, Energization of 3 phase line, Line clearing, Pull out idle materials.
Working crews
POST SCHEDULED POWER INTERRUPTION REPORT
October 31, 2024, Thursday
As scheduled: From 6:00 AM to 3:00 PM
In Actual: From 6:00 AM to 12:30 PM
Areas Affected:
Roxas City – portion of Brgy. Adlawan, Loctugan and Bago.
Panay – Brgy. Bago Grande, Candual, Agbanban and portion of Calitan.
Accomplished: Relocation of lines, Energization of the new 3 phase line, Line clearing, Pull out idle materials.
Working crews
BT 6 Team Members: R Dili, R Delfin, N Sibugan, M Umiten and R Fuentes
BT 8 Team Members: R Distura, R Sombilla, JP Hachuela, J Arroyo and R Parohinog
BT 9 Team Members: H Delfin, RV Fadirugao, D Celoso Jr, A Daliva and F Distura
BT 10 Team Members: G Condino, C Daliva, NM Distura, JF Vallente and A Ordas
ML 1 Team Members โ€“ M Bitoon, R Durias, JJ Bereber and E Bithao
ML 3 Team Members โ€“ K Cordovero, R Distura Jr. and J Jaguio
– Line clearing contractor

Other News

๐„๐Œ๐„๐‘๐†๐„๐๐‚๐˜ ๐๐Ž๐–๐„๐‘ ๐ˆ๐๐“๐„๐‘๐‘๐”๐๐“๐ˆ๐Ž๐

December 6, 2024 (Friday) Affected Areas: ๐๐‘๐†๐˜. ๐Œ๐ˆ๐‹๐ˆ๐๐ˆ๐‹๐ˆ, ๐“๐€๐๐™๐€, ๐“๐ˆ๐™๐€, ๐๐€๐“๐Ž, & ๐๐Ž๐‘๐“๐ˆ๐Ž๐ ๐Ž๐…...

read more

Follow Us

Other Related Posts