WEEKLY ACCOMPLISHMENTS BT1

Published: January 14, 2024

January 8-10, 2024, Monday to Wednesday

BT2 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
Accomplished:
1. Relocation of poles, rehabilitation of kilowatt hour meters and line clearing at Barangay Tinaytayan, Dumarao (w/ ML -1 crew)
2. Relocation of pole and transfer of kwh meters, replacement of rotten pole and rehabilitation of kwh meter and clearing of lines at Sitio Tondo, Barangay Tabuc Sur, Panitan
3. Rehabilitation of lines at Barangay Bailan, Pontevedra
4. Hole Digging at Barangay San Esteban, Pilar