WEEKLY ACCOMPLISHMENTS BT9

Published: January 14, 2024

January 9-12, 2024, Tuesday to Friday

BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura
Accomplished:
1. Construction of 3-phase line extension at Thrulyn Glomo Rice Mill at Barangay Bagong Barrio, Tapaz
2. Pull out of 25 KVA Transformer at Sigma Municipal Hall
3. Replacement of 50 KVA transformer at Barangay Poblacion Sur, Sigma
4. Installation of 25 KVA transformer at Sigma to address low voltage problem
5. Replacement of pole and rehabilitation of kilowatt hour meters at Barangay San Esteban, Pilar