CONSOLIDATED TEAM ACCOMPLISHMENTS BT 6

Published: January 17, 2024

January 7 and January 15-16, 2024, Sunday, Monday and Tuesday

BT 6 Team Members: J Saron, F Fabella, M Batuampo, E Delos Santos and M. Deocampo
Accomplished:
1. Relocation of pole and rehabilitation of metering at Agmalobo, Ivisan
2. Clearing of lines by cutting 3 coconut trees at Agmalobo, Ivisan
3. Correction of metering and pull out idle materials at Baybay, Roxas City
4. Replacement rotten pole at Sitio Suol, Tanque, Roxas City
5. Rehabilitation of line and transfer of metering to new pole

Other News

๐‚๐€๐๐„๐‹๐‚๐Ž ๐‡๐Ž๐‹๐ƒ๐’ ๐‚๐‡๐‘๐ˆ๐’๐“๐Œ๐€๐’ ๐€๐๐ƒ ๐“๐‡๐€๐๐Š๐’๐†๐ˆ๐•๐ˆ๐๐† ๐‚๐„๐‹๐„๐๐‘๐€๐“๐ˆ๐Ž๐

The Capiz Electric Cooperative, Inc. (CAPELCO) successfully held its Christmas and Thanksgiving...

read more

๐‚๐€๐๐„๐‹๐‚๐Ž ๐‚๐Ž๐๐ƒ๐”๐‚๐“๐’ ๐ƒ๐„๐‚๐„๐Œ๐๐„๐‘ ๐‘๐„๐†๐”๐‹๐€๐‘ ๐Œ๐„๐„๐“๐ˆ๐๐† ๐€๐๐ƒ ๐“๐‡๐€๐๐Š๐’๐†๐ˆ๐•๐ˆ๐๐† ๐Œ๐€๐’๐’

The CAPELCO family once again came together in faith and fellowship for the First Friday Holy...

read more

Follow Us

Other Related Posts