(0963) 043 8339 info@capelco.com

CONSOLIDATED TEAM ACCOMPLISHMENTS BT1

Published: January 17, 2024

January 15-16, 2024, Monday and Tuesday

BT2 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
Accomplished:
1. Replacement of 3 pieces of rotten pole (mano-mano) at Sitio Malingin, Barangay Guintas, Jamindan
2. Relocation of pole and line clearing at Sitio Dodo, Barangay Agtambi, Dao
3. Replacement of rotten pole at Sitio Proper, Barangay Agtambi, Dao

Other News

Follow Us

Other Related Posts