NGCP POWER INTERRUPTION PIGGY-BACKING ACTIVITIES

Published: February 4, 2024

February 4, 2024, Sunday

Roxas City Construction and Maintenance Operation
As scheduled: From 6:00 AM to 6:00 PM
In Actual: From 6:21 AM to 5:22 PM
Maximizing the time that power is out due to NGCPs preventive maintenance activities, construction and maintenance crews conducted their own parallel activities and accomplished the following:
1. Replacement of rotten pole
2. Replacement of damaged crossarm
3. Correction of lines
4. Ressaging of lines
5. Installing stirrup clamp
6. Pull out of idle materials
7. Hotspot correction of Burgos Substation
Working crew:
BT 6 Team Members: J Saron, F Fabella, M Batuampo, E Delos Santos, N Distura, J Valiente and M Deocampo
BT 8 Team Members: G Condino, C Daliva, NM Distura, M Umiten JF Valiente and A Ordas
BT5 Team Members: R Dili, R Delfin, N Sibugan, JD Dice, and R Fuentes
M 1 Team Members – R Delfin and L Dordas
M 3 Team Members – R Aragona and L Vega
M 5 Team Members – J Avaricioand J Vidal
M 11 Team Members – P Declaro and R Elauria
M 13 Team Members – F Buday and J Taburnal
M 14 Team Members – R Hechanova and M Alsagon

Other News

Ang Presyo sang Kuryente sa Bulan sang Hunyo Nag Nubo!

𝐌𝐀𝐀𝐘𝐎 𝐍𝐆𝐀 𝐁𝐀𝐋𝐈𝐓𝐀! 𝐀𝐍𝐆 𝐏𝐑𝐄𝐒𝐘𝐎 𝐒𝐀𝐍𝐆 𝐊𝐔𝐑𝐘𝐄𝐍𝐓𝐄 𝐒𝐀 𝐁𝐔𝐋𝐀𝐍 𝐒𝐀𝐍𝐆 𝐇𝐔𝐍𝐘𝐎 𝐍𝐀𝐆 𝐍𝐔𝐁𝐎! Humalin Abril 2025,...

read more

Stay Connected with CAPELCO

𝐒𝐓𝐀𝐘 𝐂𝐎𝐍𝐍𝐄𝐂𝐓𝐄𝐃 𝐖𝐈𝐓𝐇 𝐂𝐀𝐏𝐄𝐋𝐂𝐎 in this holiday season and pay your Electric Bills on or before due...

read more

Follow Us

Other Related Posts