POST SCHEDULED POWER INTERRUPTION REPORT

Published: April 21, 2024

April 21, 2024, Sunday

As scheduled: From 6:00 AM to 8:00 AM
Actual: From 6:00 AM to 7:39 AM
Areas affected: New Road, Banica, Mongpong, Culajao, Gabuan, Dumolog, Cogon and Punta Cogon
Accomplished: Relocation of poles at Barangay Gabuan, Roxas City
Working Crews:
BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes
BT 11 Team Members: J Saron, R Fabella, M Batuampo, E Delos Santos and M Deocampo