(0963) 043 8339 info@capelco.com

CONSOLIDATED TEAM ACCOMPLISHMENTS BT6

Published: May 27, 2024

May 24-25, 2024, Friday and Saturday

BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes
Accomplished:
1. Relocation of pole at Barangay Cagay, Roxas City (DITO paid project)
2. Pull out of 37.5 KVA transformer at Arcabalo Milibili and installation of 37.5 KVA Transformer at Dinginan, Roxas City (religious fiesta)
3. Installation of 25 KVA transformer at Cabugao, Roxas City (Religious Fiesta)
4. Installation of intermediate pole at Ilamnay, Panay (FB complaint)