MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION

Published: June 2, 2024

June 1, 2024 as of 7:25 PM today

The New 15 MVA Power transformer has been properly positioned into its mounting platform and the area has been cleared of debris. Initial testing has been made and the result is positive. Working crews are now preparing the interconnections of its cable and all other accessories which is expected to take some time due to the sensitivity of the works that has to be done.