PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION

Published: June 5, 2024

June 2, 2024, Sunday

CAPELCO CONSTRUCTION CREWS
Accomplished:
1. Relocation of 2 poles and rehabilitation of kilowatt hour meters at Sitio Ayuyan, Barangay Sto. Angel, Dumalag
2. Replacement of rotten pole at Barangay Angub, Cuartero (Double circuit) and rehabilitation of kilowatt hour meters
3. Line clearing
4. Pull out of temporary 1 span 3 phase line at Dao Substation
5. Pull out of temporary connection of 13.2 and 69kv at Bypass Road, Barangay Amaga, Sigma
Working Crews:
BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes
BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog
BT 10 Team Members: G Condino, C Daliva, NM Distura, R Daliva and A Ordas
BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo
ML 1 Team Members: M Bitoon, R Durias, JJ Bereber and E Bithao
#NLBEnterprises โ€“ Line Clearing contractor

Other News

Ang Presyo sang Kuryente sa Bulan sang Hunyo Nag Nubo!

๐Œ๐€๐€๐˜๐Ž ๐๐†๐€ ๐๐€๐‹๐ˆ๐“๐€! ๐€๐๐† ๐๐‘๐„๐’๐˜๐Ž ๐’๐€๐๐† ๐Š๐”๐‘๐˜๐„๐๐“๐„ ๐’๐€ ๐๐”๐‹๐€๐ ๐’๐€๐๐† ๐‡๐”๐๐˜๐Ž ๐๐€๐† ๐๐”๐๐Ž! Humalin Abril 2025,...

read more

Stay Connected with CAPELCO

๐’๐“๐€๐˜ ๐‚๐Ž๐๐๐„๐‚๐“๐„๐ƒ ๐–๐ˆ๐“๐‡ ๐‚๐€๐๐„๐‹๐‚๐Ž in this holiday season and pay your Electric Bills on or before due...

read more

Follow Us

Other Related Posts